Wednesday, April 8, 2009

April 09

Progress on inside is slow but getting there. Electrical 1st fitting is to be completed today 8th april. Fascia and soffit to be attached today. Outside stone facing to be done next week after fascia is applied. Inside insulation is to commence today and thursday so to allow plastererer to begin slabbing upstairs etc.